renovation home
our projects
attics
bathrooms
books
brick houses
general
insurance
links
organizations
plaster
research
schedules
styles
suppliers
getting on TOH
tin ceilings
tools
water problems
old house worries
Phouka Home
|
"Spend enough time confirming the need,
and the need will go away"
- Beancounter Creed
Actually doing the work yourself -- Sequence of Renovation
- planning - wish lists, rough sketches, hold initial discussions with architects and contractors,
- obtain preliminary financing, get ballpark estimates
- Obtain permits - if you will be living in the house while working, obtain necessary occupancy permits and work permits
- Plan - make lists of materials, meet with architects, contractors
- Clean up - clean out debris and add rough weatherproofing to holes
- secure the building
- install temporary amenities such as electrical, chem toilets, hook up utilities
- do major structural work in basement - masonry, water problems, wooden underpinnings
- demolish walls, ceiling, floors
- frame structural carpentry
- attend to roof
- do weatherproofing and exterior work
- erect interior walls and curtain walls
- rough out heating, plumbing, electrical
- finish wall and ceiling surfaces
- install underlayment for finish floors install tile floors
- set plumbing and radiators, electrical
- tape drywall
- install cabinetry
- paint and wallpaper
- replace and repair trim
- finish floors
- complete misc. carpentry
Kitchen Remodeling
The Critical Path in construction
- Demolition and removal of the old kitchen: 1 day to 1 week
- Demolition of walls and removal of debrius: 3 days to 1 week
- Removal of existing flooring to be replaced: 1-3 days
- Construction of addition (if required)
- Excavation of new foundation: 1 week
- Pouring new foundation: 1 week
- Drying: 2-4 weeks
- Framing new areas: 3-4 weeks
- Roughing in plumbing and electrical: 2-3 days
- Sheetrocking for all new walls: 2-3 weeks
- Instllation fo new flooring:
- wood: 3-6 days
c
- eramic: 3-4 days
- vinyl: 1-2 days
- Delivery and Installation of new cabinets: 3days to 2 weeks
- Installation of countertops: 2-5 days
- FInishing plumbing and electrical hookups:3-5 days
- TGrimming of windows and doors: 2 days to 1 week
- installation of wall covering: 1 week
- Cleanup: 1-3 days
- Final walkthrough and isntallation of furniture: 1-2 days
|